
Moody
Church
Moody
Church seats 3,800 in theatre-style seating on a main floor
and cantilevered balcony
Business
Challenge
The Moody Church challenge was to install a complete air conditioning
system in a historical building that was never designed for
modern air conditioning. To complicate matters further, the
building’s out-dated ventilating system relied on under
floor concrete tunnels to supply outside air in through small
mushroom-shaped floor vents. The lack of mechanical cooling
resulted in extremely warm temperatures inside the building.
The Air Comfort Solution
Air Comfort determined that a roof-mounted 185-ton air-cooled
liquid chiller would be required to handle the cooling load
of the sanctuary’s main floor and two multi-function rooms
located in the lower level. A chilled glycol solution would
circulate through the cooling coils of three air handling units
located in the church’s lower level. Two 75-ton, roof-mounted,
air-cooled package units would provide cooling to the balcony
and choir seating areas via new ductwork in the attic and new
ceiling grilles installed in the 71-foot high vaulted ceiling
of the main sanctuary.
As work began, a demolition company was contracted to take apart
and remove the original air handlers located in the lower level
where the new air handling units would be installed. At the
same time, a scaffold company was hired to construct working
platforms in the 12-foot high attic space above the main sanctuary.
A concrete and bricklaying firm provided openings in one end
wall of the attic through which the majority of the new attic
ductwork would be loaded prior to installation. Finally, new
steelwork on the roof was scheduled to support the new chiller
and two new rooftop units.
The Result
Working around the church’s schedule, as well as the weather,
the project took one year to complete. The new system effectively
cools the entire church, which occupies one full city block.
The floor vents installed allow the cool air to gently “waft”
from the vent. The amount of noise generated by the new cooling
and air handling systems was considered so as not to interfere
with the church’s radio broadcasts.
The new ventilation system is controlled by a Trane building
automation system that can be easily accessed by an operator
at a desktop terminal. According to Richard Karnath, a licensed
architect who is facilities director of the church, parishioners
are singing the praises of the new system and parishioners who
were unable to attend services because of the heat are now comfortably
enjoying services.
|